Fire Protection Manual

Chapter 9

Evacuation Procedure for Drills and Actual Events

 

1.0           Purpose

Evacuation drills are conducted to familiarize staff with fire alarm and evacuation routes, test the process of accounting for all personnel known to be in the building, and evaluate staff response to an alarm. An actual event evacuation follows the same process steps as an evacuation drill minus preparation and alarm activation.

At least one evacuation drill is performed per calendar year in the following buildings by the designated Evacuation Drill Coordinator in accordance with International Fire Code; Section 405, Emergency Evacuation Drills; and, DOE G 151.1-4 Section 7.3.8, Accountability.  An actual event that causes an evacuation may serve as a qualifying “evacuation drill” if it is documented, as described, in Section 4.0, Process Steps, below.

 

Required Buildings

Building

Evacuation Drill Coordinator

Division

ARC

Tim Minga

FM

ATS, Bldg. 89

Tim Minga

FM

CEBAF Center, Bldg. 12

Jodi Patient

PHY

Counting House, Bldg. 97

Tim Minga

PHY

EEL, Bldg. 90

Jack Segal

PHY

ES&H

Mary Jo Bailey

ES&H

Hall A

Jessie Butler

PHY

Hall B

Denny Insley

PHY

Hall C

Walter Kellner

PHY

Hall D

Mark Stevens

PHY

LERF

 Steve Benson

LERF

TED, Bldg. 55

Joyce Miller

PHY

Test Lab, Bldg. 58 and

Test Lab Addition (TLA)

Phil Denny

ACCEL

SSC

Tim Minga

FM

Last updated November 17, 2021 (contact the Fire Marshal for current list)

 

2.0           Scope

This document describes the procedure used to conduct planned evacuation drills, including preparation, performance, and documentation.

3.0           Responsibilities

Note:    Management authority may be delegated to a task-qualified TJNAF employee at the discretion of the responsible manager.

3.1           Evacuation Drill Coordinator:  prepare, perform, and document evacuation drills in your assigned building

3.2       Fire Marshal

·       facilitate the activation of the fire alarm system and restoration to normal

·       review, and if appropriate, approve, record, and distribute completed Evacuation Drill Reports

·       update the Fire Evacuation Drill Completion Record and document such in accordance with department procedures

3.3       Security Personnel:  when advised, respond according to established procedures

4.0           Process Steps

Unless otherwise stated, the Evacuation Drill Coordinator performs the following.

4.1           Prepare for an Evacuation Drill

Step 1:         Recruit Monitors as needed

Step 2:         Assemble Monitors and Fire Marshal & discuss drill responsibilities

·       Monitors

o   ensure the alarm can be heard in assigned area

o   ensure all rooms are cleared of personnel

o   assist as needed

o   report to Evacuation Drill Coordinator when all personnel have evacuated the assigned area

o   proceed to designated muster point

o   monitor the muster point, ensuring no one re-enters the building until the “All Clear” is announced

·        Fire Marshal

o   activate the fire alarm system

o   disengage the alarm

·       Evacuation Drill Coordinator

o   time the evacuation (record start and end times)

o   provide the “All Clear” notification to those at the muster point

o   complete the Evacuation Drill Report

Step 3:         Coordinate a date and time with the Fire Marshal

·       Drills should not interfere with planned activities that may be seriously impaired by a disruption (e.g., conferences, large training classes, etc.).

·       Reschedule the drill if the weather is unacceptable. (If you reschedule, communicate with both the Fire Marshal and Security personnel.)

Step 4:         Notify On-site Security of the planned date and time.

4.2           Perform the Evacuation Drill

Step 1:         Equipment

·       blank Evacuation Drill Report

·       pen

·       stopwatch

Step 2:         Position the Monitors

Step 3:         Initiate the drill

·       Signal the Fire Marshal to activate the fire alarm system

·       Start the timer

·       Do not allow anyone to re-enter the building until authorized

·       Ensure all Monitors report in

Step 4:         Conclude the drill; when all Monitors have reported in:

·       Signal the Fire Marshal to silence the alarm

·       Stop the timer

·       Notify the Fire Department Incident Commander (FDIC) or Fire Marshal of the status of evacuation

·       When authorized by the FDIC or Fire Marshal, notify those at the muster point that they may re-enter the building

4.3           Document the Evacuation Drill

Step 1:         Complete the Evacuation Drill Report and submit it to the Fire Marshal for review and approval.

Step 2:         Upon approval, the Fire Marshal records and distributes the report to appropriate Division Safety Officer(s) and the ES&H Reporting Officer.

5.0           References

·       International Code Council Inc.; International Fire Code 2021

·       DOE O 151.1C Requirements for Annual Building Evacuation Drills

·       Jefferson Lab Fire Evacuation Drill Completion Record

6.0           Revision History

rev

summary

date

1.8

triennial review

- updated Required Buildings table under 1.0

- added note to Responsibilities section 3.0

- made general edits and format updates (bullets, spacing, revision summary to history & table format, etc.)

05.19.2022

1.7

updated Evacuation Drill Coordinators and the Fire Evacuation Drill Completion Record

10.23.2017

1.6

updated Fire Evacuation Drill Completion Record

06.02.2016

1.5

periodic review; updated Evacuation Drill Coordinators for Counting House and LERF (formerly FEL)

02.18.2016

1.4

- changed evacuation drill coordinators for: Hall C - W.Kellner to A.Kenyon; TEDF - T.Renzo to M.Bennett; Test Lab - T.Renzo to R.Bennett

- updated Fire Evacuation Drill Completion Record in 5.0 References per T.Minga

11.25.2013

1.3

changed evacuation drill coordinator for FEL from D.Walker to J.Coleman per T.Minga

10.18.2013

1.2

qualifying periodic review; updated to change evacuation drill coordinators

09.17.2013

1.1

updated to coordinate procedure with current laboratory operations

01.30.2012

1.0

updated to denote required buildings, clarify responsibilities, and detail process steps

04.01.2011

 

 

 

 

 

 

ISSUING AUTHORITY

AUTHOR

APPROVAL DATE

NEXT REVIEW DATE

rev

 

 

Fire Protection Department

Tim Minga

05.19.2022

05.19.2025

1.8

 

This document is controlled as an online file.  It may be printed but the print copy is not a controlled document. 

It is the user’s responsibility to ensure that the document is the same revision as the current online file.  This copy was printed on 5/19/2022.